Refit Project Update - Q4 2022
The last two months have been full of activity and progress! Having Escargot on the water for nearly six weeks was an invaluable experience, …

The last two months have been full of activity and progress! Having Escargot on the water for nearly six weeks was an invaluable experience, …

The third quarter of 2022 was a period of significant progress on our vessel's refit. With the arrival of our new FIMEA N80L motors at the end of …

Progress over the last three months has been focused heavily on resolving our propulsion issues. The highlight of this quarter is that we have …

We're back in the warehouse after a week of semi-successful sea trials. The past few months have been productive. We've brought our solar charging …

While only a month has passed since our last update, the progress has been immense. We have completed a multitude of critical tasks, and Escargot is …

The fourth quarter marked a major turning point in our refit project with the arrival of the complete electric propulsion system in Alicante. This …

Following a slower pace in the second quarter, we've implemented a new strategy of visiting the shipyard in Alicante monthly. This hands-on approach …

The last three months have been a classic refit story of progress and patience. While the pace has been slower than we originally planned, we've …

The refit of the Escargot has begun! After four months of hard work by the shipyard workers, we're excited to share our first major update. Our …