Second Sea Trial

Second Sea Trial

The eagerly awaited date of the launch in the Bay of Alicante is finally here. The goals are to check that the new FIMEA N80L motors are working as …

Refit project update - Q3 2021

Refit project update - Q3 2021

Following a slower pace in the second quarter, we've implemented a new strategy of visiting the shipyard in Alicante monthly. This hands-on approach …

Refit project update - Q2 2021

Refit project update - Q2 2021

The last three months have been a classic refit story of progress and patience. While the pace has been slower than we originally planned, we've …

Refit project update - Q1 2021

Refit project update - Q1 2021

The refit of the Escargot has begun! After four months of hard work by the shipyard workers, we're excited to share our first major update. Our …

Resource studies on electric boats

Resource studies on electric boats

I started thinking about how solar electric boats work and are designed and how to potentially build one, after seeing the performance of the …